Project Profile: Churchill Container Plant Relocation

p1 group_churchill container

When P1 Group Proactive Solutions Consultant Ann L. went on a cold call with Churchill Container, she learned they were getting ready to relocate their operations to a new facility.

Even though Churchill鈥檚 mechanical work was covered by another contractor, Ann told them about P1 Group鈥檚 additional capabilities and the client expressed interest in having our Millwright and Electrical experts look over their new plant.

鈥淭his is a great example of a project that followed a process of sales making first contact and the rest of the team following through to be awarded the project,鈥 Project Manager Jim N. said.

Having the capabilities of Millwrights adds to the value of P1 Group鈥檚 strong diversified capabilities.

P1 Group ended up landing both the Electrical and Millwright work for this client, leading to a contract over $1 million. The project was completed in February, 2018.

designs and produces branded plastic container packaging for clients who value package design as a marketing tool. Churchill Container company is Safety Quality Food (SQF) Level 2 certified.

churchill_container

p1 group_millwrights_churchill

Scope of Work

Designed, provided and installed (1) storage mezzanine with a capacity of 150 lbs./sq. ft. that was 32鈥橶x83鈥橪x15鈥橦.

  • Design included (18) 5x5x3 piers to support platform
  • Design included area underneath platform to be enclosed with prefabricated panels creating a maintenance shop and pump room.
  • Design included (2) 10x10x10 pre-fabricated offices to be installed on the top of the mezzanine.

Designed and installed (1) Fork Truck Ramp 14鈥-6鈥漌 x 40鈥-0鈥 L

Designed and installed (1) Silo foundation 18Wx50Lx2鈥橠

Designed and installed (6) foundation footings for Chiller Tower

Designed, provided and installed (1) pre-fabricated area 24Wx40Lx8H underneath existing mezzanine.

Designed, provided and installed (1) pre-fabricated grinding room 25Wx26Lx16H.

Designed, provided and installed (1) pre-fabricated maintenance office 12Wx18Lx10H

Designed, provided and installed (1) manufacturing firewall 180鈥-0鈥滾x24鈥-0鈥滺

Included (1) Fire rated 12x12 roll-up door and (1) Fire rated 10x10 roll-up door

Designed, provided and installed (3) 8020 fenced areas for maintenance storage and maintenance repair.

Provided services to relocate (4) plastic mold machines, (2) robot cells, (2) color printers (2) grinders (1) shrink wrapper and misc. shop equipment. Equipment was relocated from existing facility in Shawnee Mission to new facility in Lenexa.

  for a time lapse video of the plant setup.