P1 Group installed new critical power with paralleling switchgear and new generators to support DST’s functioning data center. All equipment was installed and brought online while the data center was in full operation.
P1 handled: installation of medium voltage generators, transfer switches, and associated building critical switchgear; building power, lighting and fire alarm; lightning protection, and access control systems; and live data center critical power re-configuration.
Services Provided
-
Electrical Construction
-
Controls
Project Details
Kansas City, MO
JE Dunn Construction